New Building Update

New Building Update

Since the holidays the steel frame of the new build is completed and floor slab installation to all areas, fire proof coatings to all perimeter steels, grouted ground, and roof slabs, and they have started boarding to block A and B which is the hall and the rectangular block you can see nearest the driveway.

Externally the ground formation has been completed and base course tarmac laid ahead of programme to 70% of external areas. The benefit of this is it will provide the builders with a safe and clean site for future work progression. We are loving watching the updates and look forward to visiting the site again soon. Watch this space for more details.